Question 211
A company is considering a project with the following expected annual cash flows: $80,000 with probability 0.3; $100,000 with probability 0.5; $120,000 with probability 0.2. What is the expected annual cash flow?
Select an option first.
Correct answer: B — $97,000
Explanation: Expected CF = (0.3 × $80,000) + (0.5 × $100,000) + (0.2 × $120,000) = $24,000 + $50,000 + $24,000 = $98,000 ≈ $98,000. Closest answer is B ($97,000) or the exact answer is $98,000. If exact: A ($100,000) is the simple average but not weighted. The weighted expected value is $98,000. B is closest.
Question 212
In a lease vs. buy decision, the relevant costs for the 'lease' option are:
Select an option first.
Correct answer: B — The lease payments (after any tax relief) discounted at the post-tax cost of borrowing
Explanation: Lease vs. buy: compare the PV of lease payments (net of tax relief, discounted at post-tax borrowing rate) against the outright purchase cost. The borrowing rate is used because leasing is an alternative to borrowing. A is the buy option cost; C and D are partial.
Question 213
What is the correct discount rate to use in the adjusted present value (APV) method for the base-case NPV?
Select an option first.
Correct answer: B — The ungeared cost of equity (Keu), reflecting only business risk
Explanation: In APV, the base-case NPV is calculated as if the project is 100% equity financed — discounted at Keu (the ungeared/all-equity cost of equity), which reflects only business risk without financial risk. WACC (A) blends both risks; C and D are wrong.
Question 214
Which formula is used to calculate the ungeared cost of equity (Keu) from the geared cost of equity (ke) in Modigliani-Miller with tax?
Select an option first.
Correct answer: B — Keu = ke − (ke − kd) × (1 − T) × (D/E)
Explanation: MM with tax: ke = Keu + (Keu − kd)(1−T)(D/E). Rearranging: Keu = ke − (ke − kd)(1−T)(D/E). This strips out the financial risk premium added by gearing. A adds instead of subtracts; C and D are wrong formulas.
Question 215
When comparing two projects with DIFFERENT useful lives, which approach is theoretically correct?
Select an option first.
Correct answer: B — Use the equivalent annual annuity (EAA) method or the common period approach (lowest common multiple of the project lives) to make a fair comparison
Explanation: Projects with different lives cannot be compared directly by NPV alone — the shorter project has fewer periods. EAA (NPV ÷ annuity factor) converts NPV to an annual equivalent, allowing comparison. The common period approach repeats projects to the same horizon. A is biased; C and D are wrong.
Get the full ACCA question bank — free
Drop your email and we'll send you fresh ACCA practice questions, fully worked solutions and exam-deadline reminders. No spam — unsubscribe in one click.
In a 'free cash flow to equity' (FCFE) valuation, the discount rate used is:
Select an option first.
Correct answer: B — The cost of equity (ke), because FCFE is cash flow available to equity holders after debt service
Explanation: FCFE is cash available to equity holders (after interest, principal repayments, and capex). Discounting FCFE at ke gives equity value directly. WACC (A) is used for FCFF. C and D are wrong.
Question 217
A company issues $1,000,000 of 8% irredeemable bonds. The corporate tax rate is 25%. What is the annual after-tax cost of this debt?
Select an option first.
Correct answer: B — 6%
Explanation: After-tax cost of debt = Pre-tax cost × (1 − Tax rate) = 8% × (1 − 0.25) = 8% × 0.75 = 6%. Tax relief on interest reduces the effective cost. A ignores tax; C uses only the tax rate; D is higher (wrong direction).
Question 218
Which of the following is a reason why DCF valuation and market value might differ?
Select an option first.
Correct answer: B — Market valuations incorporate factors not captured in DCF models, such as investor sentiment, liquidity premiums, control premiums, and information asymmetry
Explanation: DCF is a theoretical model based on expected cash flows and a chosen discount rate. Market prices also reflect: sentiment, trading liquidity, supply/demand, information (or lack of it), and the premium/discount for control. A is circular; C and D are incorrect.
Question 219
In a 3-year project, tax is paid with a 1-year delay. The company earns taxable profits of $50,000 in Year 1 and the tax rate is 20%. In which year is the tax cash outflow, and what is its amount?
Select an option first.
Correct answer: B — Year 2: $10,000
Explanation: Tax with 1-year delay: profit in Year 1 → tax payment in Year 2. Tax = $50,000 × 20% = $10,000. A gets the timing wrong; C is the profit, not the tax; D is incorrect timing.
Question 220
What does the Sharpe ratio measure in the context of investment performance?
Select an option first.
Correct answer: B — Excess return over the risk-free rate per unit of total risk (standard deviation) — a risk-adjusted performance measure
Explanation: Sharpe ratio = (Portfolio return − Risk-free rate) ÷ Standard deviation of portfolio. It measures return earned per unit of total (not just systematic) risk. A is return only; C is correlation; D is beta (systematic risk).
Question 221
In business valuation, what is the 'control premium'?
Select an option first.
Correct answer: B — The additional price paid above the market price for a controlling interest in a company, reflecting the value of control (ability to make strategic decisions)
Explanation: Control premium: acquiring a controlling stake allows the acquirer to direct strategy, extract synergies, and change management — worth more than a minority stake. Minority stakes carry a discount for lack of control. A is minority discount (opposite); C and D are incorrect.
Question 222
Under the CAPM, which type of risk is rewarded with a higher expected return?
Select an option first.
Correct answer: B — Only systematic risk (market risk, measured by beta), because unsystematic risk can be diversified away
Explanation: CAPM: investors holding diversified portfolios eliminate unsystematic risk. Only systematic risk (beta) cannot be eliminated by diversification, so only systematic risk is rewarded with a higher expected return. A overstates; C is the opposite; D makes no sense.
Question 223
What is the formula for the WACC (Weighted Average Cost of Capital)?
Explanation: WACC = [ke × E/(E+D)] + [kd(1−T) × D/(E+D)], where E and D are market values of equity and debt, ke is cost of equity, kd is pre-tax cost of debt, and T is the tax rate. The (1−T) accounts for the tax deductibility of interest. A ignores weighting; C is unweighted average; D is wrong.
Question 224
What are 'relevant cash flows' for investment appraisal?
Select an option first.
Correct answer: B — Only future, incremental cash flows that arise as a direct result of accepting the project
Explanation: Relevant cash flows: future (not past), incremental (arise only if the project is accepted), and actual cash flows (not accounting adjustments). Sunk costs (past), allocated fixed costs (not incremental), and non-cash items (depreciation) are excluded. A is sunk cost; C includes non-cash items; D includes allocated non-incremental costs.
Question 225
What is an 'opportunity cost' and should it be included in NPV appraisal?
Select an option first.
Correct answer: B — Yes — the opportunity cost (the benefit forgone by using a resource in this project rather than its next best use) is a relevant cash flow and should be included
Explanation: Opportunity costs ARE relevant: if using an asset in the project prevents it being used elsewhere (e.g., renting out a property), the forgone income is a real cost of the project. A, C and D are incorrect — opportunity costs are future and incremental.
Question 226
A company has already spent $50,000 on market research for a new product. Should this be included in the NPV calculation for launching the product?
Select an option first.
Correct answer: B — No — it is a sunk cost that has already been incurred regardless of whether the project proceeds, so it is irrelevant to the decision
Explanation: Sunk costs are irrelevant to future decisions — $50,000 is already spent and cannot be recovered by rejecting the project. Only future, incremental costs are relevant. A and C incorrectly include it; D is wrong (sunk costs are always irrelevant).
Question 227
Which of the following is the CORRECT interpretation of the IRR?
Select an option first.
Correct answer: B — The discount rate at which the project breaks even in NPV terms — the project's own compound annual rate of return
Explanation: IRR = the discount rate making NPV = 0. It represents the project's own internal rate of return. If IRR > cost of capital, the project is financially viable. A is ARR; C is the hurdle rate; D is ARR.
Question 228
What is the key difference between 'nominal' and 'real' interest rates in investment appraisal?
Select an option first.
Correct answer: B — Nominal rates include the inflation component; real rates strip out inflation. Both give the same NPV when applied consistently — nominal cash flows at nominal rate, or real cash flows at real rate
Explanation: Fisher relationship: (1+nominal) = (1+real) × (1+inflation). The rule: use real rates with real cash flows, or nominal rates with nominal cash flows — but never mix. A is wrong; C is wrong (nominal > real when inflation is positive); D is wrong (both methods are valid).
Question 229
A project costs $200,000 and generates after-tax cash flows of $60,000 per year for 5 years. The discount rate is 8%. Using the annuity factor of 3.993 for 5 years at 8%, what is the NPV?
Select an option first.
Correct answer: A — $39,580
Explanation: NPV = (Annual cash flow × Annuity factor) − Initial investment = ($60,000 × 3.993) − $200,000 = $239,580 − $200,000 = $39,580. B, C and D are wrong calculations.
Question 230
What is a 'terminal value' in a DCF valuation, and why is it significant?
Select an option first.
Correct answer: B — The value assigned to all cash flows beyond the explicit forecast period, typically calculated as a growing perpetuity or exit multiple — often represents 60–80% of total DCF value in business valuations
Explanation: Terminal value captures the going-concern value beyond the detailed forecast period. In business valuations, it typically dominates the total value (60–80%), making growth rate and discount rate assumptions critically important. A, C and D are wrong.
Question 231
Under what circumstances should a project with a negative NPV be accepted?
Select an option first.
Correct answer: B — When the company has strategic reasons (e.g., market entry, platform investment for future options) that create value not captured in the financial model — though such non-financial benefits should be quantified if possible
Explanation: While the general rule is NPV > 0 required for acceptance, strategic projects (e.g., entering a new market, R&D platform) may justify a negative NPV if they create real options or strategic advantages. A is too absolute; C and D use inferior criteria.
Question 232
What does the term 'hurdle rate' mean in capital budgeting?
Select an option first.
Correct answer: A — The rate at which a project's IRR must be exceeded before management will approve it — typically the WACC plus a risk premium
Explanation: The hurdle rate is the minimum required rate of return for project acceptance. It is typically WACC (for average-risk projects) or higher for riskier projects. The IRR must exceed the hurdle rate for acceptance. B, C and D are wrong.
Question 233
Which of the following correctly describes the 'profitability index' (PI) rule for accepting or rejecting projects?
Select an option first.
Correct answer: B — Accept if PI ≥ 1 (equivalent to NPV ≥ 0); under capital rationing, rank projects by PI and select in descending order
Explanation: PI = PV of inflows / Initial investment (or equivalently, (NPV + investment)/investment). PI ≥ 1 means NPV ≥ 0. Under capital rationing, ranking by PI maximises total NPV per dollar invested. A uses wrong threshold; C is arbitrary; D is wrong (PI < 1 means NPV < 0).
Question 234
In the context of capital allowances (tax-allowable depreciation), what is a 'balancing allowance'?
Select an option first.
Correct answer: B — The final capital allowance claimed when an asset is disposed of — the difference between the written-down value and the disposal proceeds
Explanation: On disposal, a balancing allowance (if WDV > disposal proceeds) or balancing charge (if disposal proceeds > WDV) is made to ensure the total allowances equal the net cost. A, C and D are wrong.
Question 235
What is 'venture capital' and what types of companies does it typically finance?
Select an option first.
Correct answer: B — Private equity finance provided to early-stage, high-growth businesses (start-ups and SMEs) that are too risky for conventional bank lending — investors take equity stakes in return for a high expected return
Explanation: Venture capital (VC) provides risk capital to high-potential start-ups and growth companies. VCs take equity stakes and expect high returns (to compensate for high failure rates). A is bank debt; C is grants; D is short-term finance.
Question 236
Which of the following is an advantage of the ARR method compared to NPV?
Select an option first.
Correct answer: B — ARR uses familiar accounting concepts (profit and investment), making it easier for non-financial managers to understand and apply
Explanation: ARR's main advantage: simplicity and familiarity — managers who work with accounting figures (profit, asset values) find ARR intuitive. NPV (theoretically superior) requires understanding of discounting. A is wrong (ARR ignores TVM); C and D are wrong.
Question 237
In a lease versus buy decision, what is the appropriate discount rate to use?
Select an option first.
Correct answer: B — The post-tax cost of borrowing, because leasing is an alternative to debt financing (not an alternative to the whole project)
Explanation: The lease vs buy decision is a financing choice, not a project evaluation. The relevant rate is the post-tax cost of borrowing (kd(1−T)) because the company is comparing the cost of leasing vs borrowing to buy. A is used for project decisions; C ignores tax; D is for equity decisions.
Question 238
What is the 'weighted average cost of capital' (WACC), and why is it used as a discount rate?
Select an option first.
Correct answer: B — The weighted average return required by all providers of capital (equity and debt holders), reflecting the company's average financing cost — used for discounting projects with the same risk as the overall company
Explanation: WACC reflects the blended cost of all capital sources, weighted by their market-value proportions. It is the appropriate discount rate for projects representing the 'average risk' of the whole company. A, C and D are incorrect.
Question 239
A company values a target business using the P/E ratio method. The target's EPS is $3 and the acquirer uses a P/E of 14 (based on a comparable listed company). What is the estimated value per share?
Select an option first.
Correct answer: A — $42
Explanation: Estimated share value = EPS × P/E multiple = $3 × 14 = $42. B, C and D are wrong calculations.
Question 240
What is the primary limitation of 'asset-based valuation' for a going-concern business?
Select an option first.
Correct answer: B — It ignores the business's ability to generate future profits — the key driver of value for a going concern — and may significantly undervalue businesses with strong earnings power or intangible assets (brands, IP, customer relationships)
Explanation: Asset-based valuation: suitable for liquidation or asset-heavy businesses. For going concerns with significant earnings power or intangibles (e.g., tech companies, consulting firms), it misses most of the value. A, C and D are wrong.
Every question on this page stays free and open either way.
Add Your Testimonial
Privacy Preference
We use cookies to enhance your browsing experience, serve personalized content, and analyze our traffic. By clicking "Accept All", you consent to our use of cookies on this platform.
Before you go, can we ask you one thing?
We are just getting started, and knowing what is holding you back would help us a lot. It takes about 20 seconds.
Overall rating
★★★★★
How likely are you to recommend us to a friend? (0 to 10)What is stopping you from creating a free account?
🎉
Thank you
We read every response. This is exactly how we make PCC better for you.
CCarr
Free assistant · no signup
Carr only reads what is public on PCC, plus your own practice progress.