Question 361
The total direct material cost variance equals:
Select an option first.
Question 362
Which of the following would cause a favourable labour efficiency variance?
Select an option first.
Question 363
A variable overhead efficiency variance arises because:
Select an option first.
Question 364
A favourable fixed overhead expenditure variance means:
Select an option first.
Question 365
What does a nil (zero) variance mean?
Select an option first.
Get the full ACCA question bank — free
Drop your email and we'll send you fresh ACCA practice questions, fully worked solutions and exam-deadline reminders. No spam — unsubscribe in one click.
Want to save your score and take a full mock exam? Create a free account →
Question 366
The sales volume profit variance (under absorption costing) uses standard PROFIT per unit (not contribution). Why?
Select an option first.
Question 367
Which of the following variances would be the primary responsibility of the purchasing manager?
Select an option first.
Question 368
Which variance compares actual revenue with standard revenue for the actual quantity sold?
Select an option first.
Question 369
When would a favourable sales volume variance and an adverse sales price variance occur simultaneously?
Select an option first.
Question 370
The direct labour rate variance is adverse when:
Select an option first.
Question 371
Direct labour efficiency variance is FAVOURABLE when:
Select an option first.
Question 372
Standard: 6 kg at 4/kg = 24/unit. Actual output: 2,000 units. Actual: 13,000 kg purchased and used at 3.80/kg. Calculate material price and usage variances.
Select an option first.
Question 373
Standard: 4 hours at 12/hr per unit. Actual output: 500 units. Actual hours: 1,900; actual pay: 24,700. Calculate rate and efficiency variances.
Select an option first.
Question 374
Budget: FO 100,000, production 5,000 units. Actual: FO 104,000, production 5,500 units. Calculate expenditure and volume variances.
Select an option first.
Question 375
A planning and operational variance split is used. Original standard material: 5 kg at 6/kg. During period, market price rose to 7/kg (revised standard). Actual: 5,200 kg used for 1,000 units at 7.20/kg. Calculate planning and operational variances.
Select an option first.
Question 376
Budget: sales 4,000 units at 80 each. Actual: 4,200 units at 77 each. Standard variable cost 50/unit. Calculate sales price and sales volume contribution variances.
Select an option first.
Question 377
A company uses a standard costing system. Budget profit was 50,000 but actual profit is 38,500. The sales volume variance is 6,000 adverse and the sales price variance is 4,000 favourable. Total cost variances are 9,500 adverse. Reconcile budgeted to actual profit.
Select an option first.
Question 378
Variable overhead: standard rate 4/hr; standard 3 hrs/unit. Actual output 600 units; actual variable overhead 7,800; actual hours 1,900. Calculate variable overhead expenditure and efficiency variances.
Select an option first.
Question 379
Budgeted sales: 3,000 units at 50 each, standard variable cost 30. Actual: 2,800 units sold at 53 each, variable cost 29. Calculate sales price variance, sales volume contribution variance, and variable cost variance.
Select an option first.
Question 380
What might cause an adverse sales volume variance alongside a favourable sales price variance?
Select an option first.
Question 381
A company budgets 1,500 units at standard cost. Actual output: 1,650 units. Fixed overhead budget: 45,000. Actual fixed overhead: 43,500. OAR per unit: 30. Calculate both fixed overhead variances and the net variance.
Select an option first.
Question 382
Direct material: standard 8 kg at 5/kg=40/unit. Actual output: 400 units. Actual: 3,400 kg purchased and used at 4.80/kg. Calculate price and usage variances.
Select an option first.
Question 383
Labour data: Standard 2.5 hrs at 11/hr. Actual output 3,200 units. Actual hours: 7,500. Total wages: 88,500. Calculate rate and efficiency variances.
Select an option first.
Question 384
A company uses standard costing. Budget output: 5,000 units. Fixed overhead: 75,000. OAR=15/unit. Actual output: 4,600 units. Actual FO: 78,000. The fixed overhead volume variance is:
Select an option first.
Question 385
Standard cost card: Materials 3kg at 8=24; Labour 2hrs at 10=20; Variable OAR 2hrs at 4=8; Fixed OAR 2hrs at 6=12. Total=64/unit. Budget: 5,000 units. Calculate the fixed overhead OAR and total budgeted fixed overhead.
Select an option first.
Question 386
When should a variance be investigated?
Select an option first.
Question 387
Standard: 4 hours at 15/hr. Actual output: 1,000 units. Actual hours: 3,800; actual wages: 59,280. Calculate idle time variance if 200 hours were idle (not worked productively).
Select an option first.
Question 388
A favourable labour efficiency variance could be CAUSED BY (identify the most likely cause from an operational perspective):
Select an option first.
Question 389
Which of the following explains why planning variances and operational variances are separated?
Select an option first.
Question 390
Budgeted fixed overhead: 36,000. Budgeted units: 4,000. OAR: 9/unit. Actual units: 3,500. Actual FO: 37,000. What is total fixed overhead variance?
Select an option first.
More free ACCA topics

Before you go, can we ask you one thing?

We are just getting started, and knowing what is holding you back would help us a lot. It takes about 20 seconds.

Overall rating
★ ★ ★ ★ ★
How likely are you to recommend us to a friend? (0 to 10)
What is stopping you from creating a free account?