Question 151
What is the primary purpose of a budget in an organisation?
Select an option first.
Correct answer: B — To quantify plans, allocate resources, and provide a benchmark for performance control
Explanation: B is correct: a budget translates plans into financial terms, authorises spending, coordinates activities across departments, motivates managers and provides a yardstick against which actual results are compared. A is wrong — tax calculation is the domain of tax accounting. C is wrong — budgets support, not replace, management judgement. D is wrong — reporting historical results is a function of management reporting, not budgeting.
Question 152
Which of the following is NOT a purpose of budgeting?
Select an option first.
Correct answer: C — Eliminating the need for strategy
Explanation: C is correct (it is NOT a purpose): budgeting does not eliminate the need for strategy — in fact, budgets operationalise strategy. The genuine purposes of budgeting are planning, control, communication, motivation and co-ordination. A is a genuine purpose. B is a genuine purpose. D is a genuine purpose.
Question 153
A master budget consists of:
Select an option first.
Correct answer: D — All functional budgets combined into an overall plan
Explanation: D is correct: the master budget is the culmination of all functional budgets (sales, production, materials, labour, overheads) and includes a budgeted income statement, budgeted balance sheet and cash budget. A is wrong — the cash budget is one component of the master budget. B is wrong — capital expenditure is one component. C is wrong — this partially describes the master budget's outputs but misses the functional budgets that feed into it.
Question 154
The budget that is typically prepared first in the budget-setting process is the:
Select an option first.
Correct answer: C — Sales budget
Explanation: C is correct: the sales budget comes first because revenue drives most other budgets. Production, materials, labour and overhead budgets are all derived from what the business plans to sell. A is wrong — the production budget depends on the sales budget. B is wrong — the labour budget depends on production requirements. D is wrong — the cash budget is one of the last to be prepared, incorporating all receipts and payments.
Question 155
A principal budget factor (limiting budget factor) is:
Select an option first.
Correct answer: B — The constraint that limits the organisation's activities and must be identified before other budgets are set
Explanation: B is correct: the principal budget factor is the key constraint on the organisation — usually sales demand, but sometimes material availability, skilled labour or machine capacity. It must be identified first because all other budgets must be consistent with it. A is wrong — detail level is not the criterion. C is wrong — seniority of the preparer doesn't define the principal budget factor. D is wrong — monetary value is irrelevant.
Get the full ACCA question bank — free
Drop your email and we'll send you fresh ACCA practice questions, fully worked solutions and exam-deadline reminders. No spam — unsubscribe in one click.
Correct answer: B — Taking last period's budget and adjusting it for expected changes
Explanation: B is correct: incremental budgeting starts from the prior period's budget and makes adjustments for known changes (e.g. inflation, volume changes). It is simple but can perpetuate inefficiency. A is wrong — that describes zero-based budgeting. C is wrong — that describes scenario-based planning. D is wrong — optimisation is a separate technique.
Question 157
Zero-based budgeting (ZBB) requires managers to:
Select an option first.
Correct answer: B — Justify every item of expenditure from scratch, as if starting from zero
Explanation: B is correct: ZBB requires every cost to be justified and approved anew each period — nothing is automatically carried forward. It challenges existing spending patterns and can eliminate wasteful costs. A is wrong — that is incremental budgeting. C is wrong — ZBB applies to all expenditure. D is wrong — ZBB covers all budgets, not just capital.
Question 158
Which of the following is a DISADVANTAGE of zero-based budgeting?
Select an option first.
Correct answer: C — It is very time-consuming and costly to implement
Explanation: C is correct: ZBB's main drawback is the substantial time and management effort required to justify all expenditure from scratch every period. A is wrong — that is an advantage of ZBB. B is wrong — that is an advantage. D is wrong — preventing automatic roll-forward is a feature and advantage, not a disadvantage.
Question 159
A fixed budget is one that:
Select an option first.
Correct answer: A — Remains unchanged regardless of actual activity level
Explanation: A is correct: a fixed budget is prepared for a single planned activity level and is not adjusted when actual activity differs — making it unsuitable for performance appraisal when actual volume differs from budget. B is wrong — that describes a flexible budget. C is wrong — monthly updating describes rolling budgets. D is wrong — fixed budgets include all costs, not just fixed ones.
Question 160
A flexible budget is useful because it:
Select an option first.
Correct answer: B — Adjusts for the actual volume of activity, making performance comparisons meaningful
Explanation: B is correct: a flexible budget is re-expressed at the actual activity level, separating volume differences from efficiency and price differences — enabling a fairer comparison of actual costs with budgeted costs for the actual output achieved. A is wrong — flexible budgets still set spending limits. C is wrong — flexible budgets are more useful for comparison but not necessarily more 'accurate'. D is wrong — variance analysis is still performed on the flexed budget.
Question 161
Which of the following best describes a rolling (continuous) budget?
Select an option first.
Correct answer: B — A budget that is continually updated by adding a new period as the most recent period expires
Explanation: B is correct: a rolling budget always maintains a full planning horizon (e.g. 12 months ahead) by dropping the most recently completed period and adding a new future period, ensuring plans are always current. A is wrong — inflation adjustment is incremental budgeting. C is wrong — scope of application doesn't define rolling budgets. D is wrong — rolling budgets include all costs.
Question 162
The production budget for a period is calculated as:
Select an option first.
Correct answer: B — Sales units minus opening inventory plus closing inventory
Explanation: B is correct: production required = budgeted sales + desired closing inventory - opening inventory. You need to produce enough to meet sales AND build up inventory to the required level, starting from what you already have. A is wrong — the formula is inverted; this would reduce production by closing inventory. C is wrong — that calculates revenue, not production units. D is wrong — that calculates cost of goods sold.
Question 163
Budgetary slack (or padding) refers to:
Select an option first.
Correct answer: B — Deliberately understating revenue or overstating cost estimates in a budget to make targets easier to achieve
Explanation: B is correct: budgetary slack occurs when managers build in extra costs or lower revenues so that actual performance easily beats the budget — making them look good while wasting resources. A is wrong — preparation time is not slack. C is wrong — that is a volume variance concept. D is wrong — cash buffer is a liquidity concept, not slack.
Question 164
Participative (bottom-up) budgeting involves:
Select an option first.
Correct answer: B — Managers at all levels contributing to the budget they will be responsible for
Explanation: B is correct: in participative budgeting, the people who will be held accountable for a budget are involved in setting it — improving information quality, buy-in and motivation, though it can also introduce slack. A is wrong — that is top-down (imposed) budgeting. C is wrong — historical data alone is not participative. D is wrong — external consultants would reduce participation.
Question 165
A cash budget differs from a profit budget because:
Select an option first.
Correct answer: B — Cash budgets focus on when cash is received and paid; profit budgets match income and expenses to the period they relate to
Explanation: B is correct: a cash budget tracks actual cash inflows and outflows (timing matters — credit sales are received later, capital purchases are paid upfront), while the profit budget follows accrual accounting matching costs and revenues to the period they earn/incur. A is wrong — depreciation appears in profit budgets but NOT in cash budgets (non-cash expense). C is wrong — cash budgets are often monthly. D is wrong — profit budgets include revenue.
Question 166
Variance analysis compares:
Select an option first.
Correct answer: B — Actual results with budgeted (or standard) results to identify and explain differences
Explanation: B is correct: variance analysis measures the difference between actual results and what was expected (budget or standard) — explaining whether differences were favourable or adverse and helping managers take corrective action. A is wrong — comparing two budgets is trend analysis. C is wrong — competitor benchmarking is not traditional variance analysis. D is wrong — that is cost classification, not variance analysis.
Question 167
A favourable variance occurs when:
Select an option first.
Correct answer: C — Actual profit is higher than budgeted profit (costs lower or revenues higher than budget)
Explanation: C is correct: a variance is favourable when the actual result is better than expected — costs below budget or revenues above budget both improve profit and are labelled favourable (F). A is wrong — actual costs higher than budget is an adverse cost variance. B is wrong — lower revenues than budget is adverse. D is wrong — loose budgets relate to slack, not the definition of favourable.
Question 168
Which of the following is an example of strategic planning?
Select an option first.
Correct answer: B — Deciding which new markets to enter over the next five years
Explanation: B is correct: strategic planning involves long-term, high-level decisions about the overall direction of the organisation — such as which markets to compete in, major capital investments, or mergers. A is wrong — weekly production targets are operational planning. C is wrong — payroll is operational. D is wrong — maintenance scheduling is tactical/operational.
Question 169
Tactical planning typically covers a time horizon of:
Select an option first.
Correct answer: B — One to three years
Explanation: B is correct: tactical planning (also called medium-term planning) bridges strategy and operations, typically covering one to three years and translating strategic goals into specific programmes and budgets. A is wrong — days or weeks are operational. C is wrong — ten to twenty years is strategic (very long-term). D is wrong — the current period is operational.
Question 170
The term 'management by exception' means:
Select an option first.
Correct answer: B — Managers focus their attention on significant variances and deviations from plan
Explanation: B is correct: management by exception allows managers to concentrate on the variances that matter — those that are significant or unexpected — rather than reviewing all activities. Minor variances within tolerance are ignored. A is wrong — reviewing every transaction is the opposite of MBE. C is wrong — it refers to management style, not seniority. D is wrong — budgets are set for all activities.
Question 171
A standard cost is:
Select an option first.
Correct answer: B — A pre-determined expected cost based on efficient operation
Explanation: B is correct: a standard cost is a carefully calculated, predetermined cost representing what a unit should cost under efficient, attainable operating conditions — used as a benchmark for comparison with actual costs. A is wrong — actual cost is recorded, not a standard. C is wrong — competitor costs are benchmarks, not standard costs. D is wrong — manager approval does not define standard cost.
Question 172
An ideal standard is set assuming:
Select an option first.
Correct answer: B — Perfect efficiency with no wastage, idle time or machine breakdowns
Explanation: B is correct: ideal standards represent perfect efficiency — every minute of labour is productive, no materials are wasted, all machines run without issue. They are rarely achieved but can be used as a long-term aspirational target. A is wrong — allowing for wastage and downtime is an attainable standard. C is wrong — above-average historical is closer to attainable or normal standard. D is wrong — maintaining current efficiency is a current standard.
Question 173
An attainable standard is set assuming:
Select an option first.
Correct answer: B — Efficient performance but allowing for normal levels of waste and downtime
Explanation: B is correct: attainable standards are the most commonly used — they assume efficient, well-managed operations but acknowledge realistic levels of downtime, material waste and human imperfection. They motivate because they are achievable but require effort. A is wrong — perfect conditions describe ideal standards. C is wrong — historical averages may not reflect what is possible with effort. D is wrong — minimum performance is a different concept.
Question 174
A direct material price variance measures:
Select an option first.
Correct answer: B — The difference between what materials actually cost and what they should have cost for the quantity purchased
Explanation: B is correct: the material price variance = (standard price - actual price) × actual quantity purchased. It isolates whether the purchasing function paid more or less than the standard price for materials. A is wrong — that is the usage variance. C is wrong — material usage, not price, relates to workforce efficiency. D is wrong — volume differences are sales variances.
Question 175
A direct material usage variance measures:
Select an option first.
Correct answer: B — The difference in cost because more or fewer materials were used than the standard quantity for actual output
Explanation: B is correct: material usage variance = (standard quantity for actual output - actual quantity used) × standard price. It measures whether production was material-efficient. A is wrong — price differences are captured by the price variance. C is wrong — the overall variance is price + usage combined. D is wrong — inventory movement is not a usage variance.
Question 176
If actual material cost is $48,000 and standard material cost for actual output is $45,000, the total material cost variance is:
Select an option first.
Correct answer: B — $3,000 adverse
Explanation: B is correct: total material variance = standard cost - actual cost = $45,000 - $48,000 = -$3,000 = $3,000 adverse (actual cost exceeded standard, so worse than expected). A is wrong — the variance is adverse because actual cost is higher. C is wrong — $48,000 is the actual cost, not the variance. D is wrong — $45,000 is the standard, not the variance.
Question 177
A direct labour rate variance is caused by:
Select an option first.
Correct answer: B — Paying workers at a different hourly rate than the standard rate
Explanation: B is correct: the labour rate variance = (standard rate - actual rate) × actual hours paid. It arises when the actual wage rate differs from the pre-set standard rate. A is wrong — taking longer is an efficiency variance. C is wrong — production volume differences are volume variances. D is wrong — material usage is a materials variance, not a labour rate variance.
Question 178
A direct labour efficiency variance is:
Select an option first.
Correct answer: A — (Standard hours for actual output - actual hours worked) × standard rate
Explanation: A is correct: the efficiency variance measures whether workers took more or less time than standard for the actual output. Favourable if fewer hours used than standard; adverse if more. B is wrong — that compares actual to budgeted hours using actual rate — not the efficiency variance formula. C is wrong — that is the rate variance formula. D is wrong — that is closer to a volume variance.
Question 179
A fixed overhead expenditure variance measures:
Select an option first.
Correct answer: B — The difference between budgeted fixed overhead and actual fixed overhead incurred
Explanation: B is correct: fixed overhead expenditure variance = budgeted fixed overhead - actual fixed overhead. It simply measures whether the business spent more or less on fixed overheads than planned. A is wrong — production volume difference is captured by the fixed overhead volume variance. C is wrong — labour efficiency is a labour variance. D is wrong — that would be variable overhead-related.
Question 180
The fixed overhead volume variance is caused by:
Select an option first.
Correct answer: B — Actual production volume differing from the budgeted production volume
Explanation: B is correct: fixed overhead volume variance = (actual output - budgeted output) × fixed overhead absorption rate per unit. When more units are produced than budgeted, more overhead is absorbed (favourable). A is wrong — actual vs budgeted overhead spend is the expenditure variance. C is wrong — labour rate is unrelated to fixed overhead volume variance. D is wrong — material prices affect material variances.
Every question on this page stays free and open either way.
Add Your Testimonial
Privacy Preference
We use cookies to enhance your browsing experience, serve personalized content, and analyze our traffic. By clicking "Accept All", you consent to our use of cookies on this platform.
Before you go, can we ask you one thing?
We are just getting started, and knowing what is holding you back would help us a lot. It takes about 20 seconds.
Overall rating
★★★★★
How likely are you to recommend us to a friend? (0 to 10)What is stopping you from creating a free account?
🎉
Thank you
We read every response. This is exactly how we make PCC better for you.
CCarr
Free assistant · no signup
Carr only reads what is public on PCC, plus your own practice progress.